Service of Nissan Almera from 1995 to 2000 in N15 body
1. General information
2. General requirements to car repairs
3. Operation and maintenance of the car
4. Petrol engines
5. Diesel engines
6. Transmission
6.1. Coupling
6.2. Mechanical transmission
6.2.1. General information
6.2.2. Removal and installation of the transmission
6.2.3. Dismantling of the transmission
6.2.4. Dismantling of a main shaft
6.2.5. Assembly of a main shaft
6.2.6. Dismantling of a secondary shaft
6.2.7. Assembly secondary валаф
6.2.8. Dismantling and assembly of differential
6.2.9. Assembly of the transmission
6.3. Automatic transmission
6.4. Drive of forward wheels
7. Running gear
8. Steering
9. Brake system
10. Electric equipment
11. Body
12. Appendices
13. Schemes of electric equipment
 





7f435ca2


6-2-8-razborka-i-sborka-differenciala.html

6.2.8. Dismantling and assembly of differential


Fig. 4.37. Knocking-out of a pin of fastening of an axis of satellites


For dismantling of differential install a differential box in a vice with soft sponges. Beat out a pin of fastening of an axis of satellites (fig. 4.37), take an axis and take out satellites and semi-axial gear wheels.
Remove a gear wheel of the main transfer, previously having marked an arrangement of details. Take out conic bearings.
Check technical condition of details. Replace bearings if they have scratches, traces of an overheat or excessive wear. The axis of satellites should not have traces of jamming or wear, an excessive gap in the case, otherwise it needs to be replaced. The working surface of teeths of satellites and semi-axial gear wheels should not be painted or excessively worn-out.

Fig. 4.38. Measurement of axial movement of semi-axial gear wheels of the main transfer


Before assembly establish into place semi-axial gear wheels and satellites with washers. Then establish an axis of satellites. Measure axial movement of semi-axial gear wheels (fig. 4.38) which has to be no more than 0,3 mm. At bigger movement pick up washers of the corresponding thickness. Establish a new pin of fastening of an axis of satellites. Apply a layer of kontrovochny paste on bolts of fastening and establish a gear wheel of the main transfer. Tighten fixing bolts the moment of 80 N · m.

"previous page
6.2.7. Assembly secondary валаф
following page"
6.2.9. Assembly of the transmission