Service of Nissan Almera from 1995 to 2000 in N15 body
1. General information
2. General requirements to car repairs
3. Operation and maintenance of the car
4. Petrol engines
5. Diesel engines
6. Transmission
7. Running gear
8. Steering
9. Brake system
10. Electric equipment
11. Body
11.1. Main data
11.2. Repair of a body
11.3. System of heating and ventilation
11.4. Climatic installation (conditioner)
11.4.1. Gas station of climatic installation
11.4.2. Removal and installation of the compressor
11.4.3. Removal and installation of a belt of the drive of the compressor
11.4.4. Removal and installation of the protection cover of the evaporator
11.5. System of safety cushions and prednatyazhitel of seat belts
12. Appendices
13. Schemes of electric equipment
 





7f435ca2


11-4-2-snyatie-i-ustanovka-kompressora.html

11.4.2. Removal and installation of the compressor


Fig. 9.48. Fastening of the compressor of the conditioner: And — GA14DE and GA16DE engines; B — the CD20 engine (3 bolts + 1 top bolt which in the drawing is not visible)



Disconnect minus a wire from the rechargeable battery. Lift and establish a forward part of the car on supports. Pump out coolant from air conditioning system. Remove a driving compressor belt (see below). Unscrew unions on the pipelines suitable to the compressor, then muffle pipelines and openings of the compressor by means of the corresponding traffic jams. Separate the compressor coupling socket, then the thermal sensor. Turn out bolts of fastening of the compressor (fig. 9.48) and take out the compressor from below.
You make installation in the sequence, the return to removal. At the same time replace all sealing rings and a dehumidifier. Replace oil in a compressor case. Fill with coolant air conditioning system. Be convinced of lack of leak of coolant and operability of the conditioner.